Homeowner Story · 8 min read
When 'Luxury' Becomes a 6-Week Delay and a Payment Dispute
Metro Décor's finishes are undeniably premium. But the cost — in money, time, and stress — was far higher than the contract suggested.
I want to start by saying this clearly: the wall panelling and custom TV unit in my living room are genuinely among the most beautiful things I've seen in a residential interior. The craftsmen Metro Décor employ produce work at a level most firms can't match.
I also want to say this clearly: if you hire Metro Décor today, you should go in with your eyes open about what the experience will cost you beyond the contract value.
We signed with them in August 2024 for our 4BHK in DLF The Crest, Gurugram. The contract was for ₹19.8L across all rooms, with a committed handover of sixteen weeks. We are now twenty-two weeks in and have just completed a snag resolution session that took four escalation emails to schedule.
The problems began at the payment milestone stage. The contract defined Milestone 3 as payable upon "carpentry carcass completion across all bedrooms." When the invoice arrived, only two of three bedrooms were at carcass stage. When I flagged this, I was told the third bedroom was "substantially complete." I held the payment for ten days and eventually released 80% after a site visit confirmed partial progress. This kind of milestone ambiguity is where disputes start.
Communication through execution was the second major failure. The project manager who signed our contract left the company in month two. His replacement had no briefing document. We spent two full evenings re-walking the flat and re-explaining selections that were already documented. This is a process failure that a well-run studio would never allow.
The six-week delay cascaded from the above. At no point did Metro Décor proactively offer a revised timeline — I had to request it, and the first revised timeline they provided was itself missed by two weeks.
Would I hire them again? No. Would I display their work proudly? Every single day.
Project Photos
Payment Milestones
Timeline Breakdown
Detailed brief, material selections, custom furniture drawings.
Custom pieces manufactured at Metro workshop; some lead times long.
Bathroom reconfigurations, false ceiling base structure.
Ran 2 weeks over; milestone ambiguity triggered payment dispute.
Painting quality excellent; schedule still recovering from earlier delay.
Snag list required 4 escalation emails to resolve; 4 weeks over original plan.
Lessons Learned
- 1Define payment milestone triggers with zero ambiguity — "substantially complete" is a dispute waiting to happen.
- 2Require a formal project manager handover procedure in the contract if PM changes mid-project.
- 3Withhold final 10–15% of each milestone payment until trigger conditions are verified in person.
- 4Get a written revised timeline any time the original timeline is missed by more than 5 days.
- 5Luxury price does not guarantee luxury process — evaluate the firm's project management, not just its portfolio.
Homeowner Verdict
Proceed with CautionVendor: Metro Décor
₹19.8L
